ADB would need to identify more adequate indicators for power system reliability to appropriately capture the benefits of transmission projects. The formulation of specific DMFs for the different tranches of an MFF are essential to appropriately measure effectiveness and establish causality between outputs and outcomes. The indicators and targets in the DMF for future projects, prepared under the new guidelines should be closely aligned with project outcomes and outputs.
Project Name
Power Transmission Enhancement Investment Program–Tranche 2
Project Number
37192-033