Advance actions were one of the measures to reduce project startup delay. However, there seems to be inadequate clarity on implementing advance actions in the government rules, and a good mechanism to make the subproject civil works ready for execution before or right after the project becomes effective. Currently, government control over the provincial debt ceiling and implementation of relevant budget management policies also contribute to startup delays and, therefore, limit project readiness.
Project Name
Strengthening Water Management and Irrigation Systems Rehabilitation Project
Project Number
42080-013
Report Date
Report Source
Self-evaluation
Country
Sector