Pasig River Environmental Management and Rehabilitation Sector Development Program

The technical assistance contributed substantially to achieving the policy reforms envisaged under the policy loan, but longer-term and more focused assistance will be required since: (i) as a new agency, the PRRC has limited capacity to drive policy reforms; (ii) policy change requires skills, effective institutional incentives and culture change; (iii) the program is ambitious and multi-faceted, encompassing a wide range of stakeholders with a variety of interests, not necessarily linked to the policy agenda.