Harbin Water Supply Project [Loan 1995-PRC]

The project became effective on 7 January 2004, nearly 1 year after the group company was registered with the HMG’s Commercial and Industrial Bureau on 24 January 2003. Close attention should have been given to revising certain project covenants to ensure that the HMG could continue to follow up on some aspects of water pricing.

Project Name

Harbin Water Supply Project [Loan 1995-PRC]

Project Number
33177-013
Report Date
Report Source
Independent project evaluation
Report Rating