Restructuring of the Technical Education and Vocational Training System Project (Balochistan)

Inadequate review by ADB of the Planning Commission form 1 (PC-1) and inconsistencies between the PC-1 and the report and recommendation of the President (RRP) slow down project implementation. To ensure a thorough review of the PC-1 by ADB, the project officer should be required to prepare a comparative statement identifying both the similarities and differences between the PC-1 and the RRP and loan agreement, and the Planning and Development Department (PDD) should be advised on corrective measures before the loan is declared effective.

Project Name

Restructuring of the Technical Education and Vocational Training System Project (Balochistan)

Project Number
36654-013
Report Date
Report Source
Self-evaluation
Country
Report Rating
Project Cycle Stage
Preparation