Determining the appropriate flexibility, in project design and institutional arrangements, facilitates smooth implementation of an emergency assistance project. For example, ascertaining the extent of flexibility on procurement procedures, including the use of consultants and financing guidelines for government agencies, are vital considerations in a post-disaster reconstruction project. This is important especially when multiple government ministries and implementing agencies are involved in the implementation of key infrastructure components.