When implementation arrangements are revised, it is vital to streamline the approval processes to facilitate subsequent project activities. After the Government of Australia's withdrawal of funding, the delay in the approval of the changes to the implementation arrangement also significantly delayed the recruitment of implementation consultants and in designing the water supply systems. This situation could have been avoided if timely approval of such change was prioritized, which could have allowed the civil works for designing water supply systems to commence on time
Project Name
Small Towns Water Supply and Sanitation Sector Project
Project Number
36339-022
Report Date
Report Source
Validation of self-evaluation
Country
Sector
Applicability