Earthquake-Displaced People Livelihood Restoration Program

The owner-driven, in situ approach to post-disaster housing reconstruction is efficient, but only partially effective in achieving the desired outcomes. This is mainly because ensuring uniformity in construction quality and seismic standards is a major challenge when serving large populations, irrespective of the levels of awareness and training of the home owners. This challenge can be partly addressed if there is real-time impact and outcome monitoring, as well as an efficient feedback-and-response loop during the reconstruction.

Project Name

Earthquake-Displaced People Livelihood Restoration Program

Project Number
40563-013
Report Date
Report Source
Self-evaluation
Country
Report Rating