Inaccurate engineering designs at project appraisal, especially when equipment and/or components essential to the project performance are not considered, can increase project costs during project implementation and may even cause delays because of a lack of loan funds. Therefore, additional financing sources and longer implementation periods shall be considered for projects without detailed and accurate designs.
Project Name
SASEC Second Bangladesh-India Electrical Grid Interconnection Project
Project Number
44192-016
Report Date
Report Source
Self-evaluation
Country
Themes
Applicability
Project Cycle Stage
Preparation
Implementation
Keywords
Engineering designs