If consultants are required to implement, supervise, monitor, and report safeguards, any delay in their engagement can lead to gaps in the safeguards measures implemented as part of the project.
Project Name
SASEC Second Bangladesh-India Electrical Grid Interconnection Project
Project Number
44192-016
Report Date
Report Source
Self-evaluation
Country
Themes
Applicability
Project Cycle Stage
Implementation