SASEC Second Bangladesh-India Electrical Grid Interconnection Project

If consultants are required to implement, supervise, monitor, and report safeguards, any delay in their engagement can lead to gaps in the safeguards measures implemented as part of the project.

Project Name

SASEC Second Bangladesh-India Electrical Grid Interconnection Project

Project Number
44192-016
Report Date
Report Source
Self-evaluation
Country
Report Rating
Applicability
Project Cycle Stage
Implementation