Skip to main content
Evaluation Lessons
  • Home
  • Countries
    • Afghanistan
    • Armenia
    • Azerbaijan
    • Bangladesh
    • Bhutan
    • Brunei Darussalam
    • Cambodia
    • China, People's Republic of
    • Cook Islands
    • Federated States of Micronesia
    • Fiji
    • Georgia
    • Hong Kong, China
    • India
    • Indonesia
    • Kazakhstan
    • Kiribati
    • Kyrgyz Republic
    • Lao People’s Democratic Republic
    • Malaysia
    • Maldives
    • Marshall Islands
    • Mongolia
    • Myanmar
    • Nauru
    • Nepal
    • Niue
    • Pakistan
    • Palau
    • Papua New Guinea
    • Philippines
    • Republic of Korea
    • Samoa
    • Singapore
    • Solomon Islands
    • Sri Lanka
    • Taipei,China
    • Tajikistan
    • Thailand
    • Timor-Leste
    • Tonga
    • Turkmenistan
    • Tuvalu
    • Uzbekistan
    • Vanuatu
    • Viet Nam
    • Australia
    • Japan
    • New Zealand
  • Sectors
    • Agriculture, natural resources, and rural development
    • Education
    • Energy
    • Finance
    • Health
    • Industry and trade
    • Information and communication technology
    • Multisector
    • Public sector management
    • Transport
    • Water and other urban infrastructure and services
  • Themes
    • Inclusive Economic Growth
    • Environmentally Sustainable Growth
    • Regional Integration
    • Private Sector Development
    • Governance and Capacity Development
    • Gender Equity and Mainstreaming
    • Knowledge Solutions
    • Partnerships
  • About
  • Home
  • Countries
  • Sectors
  • Themes
  • About

Nuku'alofa Urban Development Sector Project

The project gender action plan (GAP) needs to be achievable and directly related to the project activities.

Project Name

Nuku'alofa Urban Development Sector Project

Project Number
42394-022
Report Date
31 Dec 2021
Report Source
Self-evaluation
Country
Tonga
Sector
Water and other urban infrastructure and services
Other urban services
Urban policy, institutional and capacity development
Urban solid waste management
Urban water supply
Applicability
Project-level
Project Cycle Stage
Preparation
Implementation
Topics
GAP

Related Lessons

Implementation delays could be minimized if project feasibility review, consultant recruitment, procurement, and government approval procedures…


Delay in HSC provision impacts timely realization of benefits of wastewater management systems.


One of the significant lessons from the project is the positive impact of early fielding of PIA (project implementation assistance) consultants.…


Tapping community organizations with proven track records is beneficial for ADB-financed community-driven development initiatives.


Pioneering activities have plenty of room for multiplier effects.


Subscribe to our mailing list

6 ADB Avenue,
Mandaluyong City
1550, Metro Manila,
Philippines

 

Phone: +632 632 4444
Fax: +632 636 2444

Other ADB Websites

ADB Compliance Review Panel
Asia Pathways (ADBI Blog)
Asia Regional Integration Center
Asian Bonds Online
Asian Development Blog
Open Access Repository
Statistical Database System

IED Social Media

LinkedIn

Twitter

YouTube

©2024 Independent Evaluation - Asian Development Bank

Footer

  • About