Improved Fiscal and Infrastructure
Management Program

Outcome objectives did
not directly link to policy actions and to outputs and therefore were not attained. If the outcome
objectives are not closely linked to outputs and are overly ambitious, it is difficult to achieve a
satisfactory outcome.

Project Name

Improved Fiscal and Infrastructure
Management Program

Project Number
51059-001
51059-002
Report Date
Report Source
Validation of self-evaluation
Country
Report Rating