Uplands Irrigation and Water Resources Management Sector Project

The establishment and staffing of project management units and inclusion of counterpart funding in government budgets prior to loan approval help prevent delays in loan effectiveness. This was another benefit that resulted from the project's application of earlier lessons on the importance of advance actions.