Proper location of the project management unit is crucial to smooth implementation. Daily coordination and supervision were initially undertaken across two distant sites: the construction implementation unit (UIP) in East Kalimantan and the project implementation consultant in West Kalimantan. This caused coordination difficulties on implementation issues arising from the field. In 2016, UIP West Kalimantan was made in charge of project management. This improved project management and coordination, making implementation smoother for the rest of the project duration.
Project Name
West Kalimantan Power Grid Strengthening Project
Project Number
41074-013
Report Date
Report Source
Self-evaluation
Country
Applicability
Project Cycle Stage
Preparation
Implementation