The successful construction of the project resulted from the strong government ownership and provides a valuable lesson on the importance of this factor in facilitating effective implementation and delivery of development results in ADB-financed projects. The Erlongshan Hydropower Company (EHC) always took the initiative in solving problems, including in the provision of design documents, timely delivery of equipment, approach to dealing with issues, and other areas. The owner's initiative guaranteed appropriate procedures and timely action on key tasks and when problems arose.
Project Name
Gansu Heihe Rural Hydropower Development Investment Program: Erlongshan Hydropower Project
Project Number
39652-023
Report Date
Report Source
Self-evaluation