The project management unit (PMU) and project implementation units (PIUs) should be staffed and consultants recruited in a timely manner to carry out the necessary work at an early stage, such as the preparation of subproject appraisal reports (SARs), land acquisition and involuntary resettlement plans (LARPs), detailed designs, and bid documents; the selection of contractors; and coordination with government agencies and other stakeholders.
Project Name
Kashkadarya and Navoi Rural Water Supply and Sanitation Sector Project
Project Number
38074-013
Report Date
Report Source
Self-evaluation
Country
Sector