Rural Health Project

Lengthy administrative processes. Implementation delays were largely caused by lengthy procurement and financial control procedures at all levels. While the project management unit (PMU) and provincial project management unit (PPMU) capacity was also an issue, the government's administrative procedures were time consuming. ADB administration was considered relatively efficient.

Project Name

Rural Health Project

Project Number