Lengthy administrative processes. Implementation delays were largely caused by lengthy procurement and financial control procedures at all levels. While the project management unit (PMU) and provincial project management unit (PPMU) capacity was also an issue, the government's administrative procedures were time consuming. ADB administration was considered relatively efficient.
Project Name
Rural Health Project
Project Number
30285-013
Report Date
Report Source
Self-evaluation
Country