Specific attributes of the internal and external environments that could impact project Implementation need to be carefully considered and addressed in project design. For example, the construction of the water treatment plant in one site (Aizawl) faced challenges because of the involvement of multiple agencies, difficult terrain, and an environment prone to natural disasters. The project’s complexity warranted meticulous planning. The Completion and commissioning of the construction works should have been complemented by a public awareness campaign.