Assam Power Sector Investment Program (Tranche 2)

A proper evaluation and approval process during project implementation can reduce noncompliance issues during the safeguard assessment. Updates to safeguard documents need to be timely completed to avoid implementataio disruptions. For example, the government land considered during project design for the construction of a substation had to be changed to private land. However, the resettlement plan was not updated.

Project Name

Assam Power Sector Investment Program (Tranche 2)

Project Number
47101-003
Report Date
Report Source
Validation of self-evaluation
Country
Report Rating
Applicability
Project Cycle Stage
Implementation