Skip to main content
Evaluation Lessons
  • Home
  • Countries
    • Afghanistan
    • Armenia
    • Azerbaijan
    • Bangladesh
    • Bhutan
    • Brunei Darussalam
    • Cambodia
    • China, People's Republic of
    • Cook Islands
    • Federated States of Micronesia
    • Fiji
    • Georgia
    • Hong Kong, China
    • India
    • Indonesia
    • Kazakhstan
    • Kiribati
    • Kyrgyz Republic
    • Lao People’s Democratic Republic
    • Malaysia
    • Maldives
    • Marshall Islands
    • Mongolia
    • Myanmar
    • Nauru
    • Nepal
    • Niue
    • Pakistan
    • Palau
    • Papua New Guinea
    • Philippines
    • Republic of Korea
    • Samoa
    • Singapore
    • Solomon Islands
    • Sri Lanka
    • Taipei,China
    • Tajikistan
    • Thailand
    • Timor-Leste
    • Tonga
    • Turkmenistan
    • Tuvalu
    • Uzbekistan
    • Vanuatu
    • Viet Nam
    • Australia
    • Japan
    • New Zealand
  • Sectors
    • Agriculture, natural resources, and rural development
    • Education
    • Energy
    • Finance
    • Health
    • Industry and trade
    • Information and communication technology
    • Multisector
    • Public sector management
    • Transport
    • Water and other urban infrastructure and services
  • Themes
    • Inclusive Economic Growth
    • Environmentally Sustainable Growth
    • Regional Integration
    • Private Sector Development
    • Governance and Capacity Development
    • Gender Equity and Mainstreaming
    • Knowledge Solutions
    • Partnerships
  • About
  • Home
  • Countries
  • Sectors
  • Themes
  • About

Search

Displaying 1 - 1 of 1

Lesson
Construction timelines in climate-affected areas need to be reliably assessed to minimize completion delays. The construction timelines for Karamyk BCP, located at altitude of 2,300 meters above sea level, were tight. The contractor faced various issues due to the harsh weather, electricity supply interruptions, and delays with the supply of materials and equipment. Combined with the contractor’s relatively low financial capacity, this resulted in a 4-year construction period versus the originally planned 15-month implementation timeline.

Project Number: 46124-001
Project Name: Central Asia Regional Economic Cooperation Regional Improvement of Border Services Project
Report Date: 11 Jul 2024

Content type

  • Lesson (1)

Countries

  • Kyrgyz Republic (1)
  • Tajikistan (1)

Sectors

  • (-) Finance (1)
    • (-) Trade finance (1)

Themes

  • Inclusive Economic Growth (1)
  • Regional Integration (1)
  • Gender Equity and Mainstreaming (1)

Report Year

  • 2024 (1)

Report Source

  • Self-evaluation (1)

Report Rating

  • Less than successful (1)

Applicability

  • Project-level (1)

Topics

  • Others (1)
  • Overambitious objectives (1)
  • Policy and reform (1)
  • Project design (3)
  • Technical (2)
  • Time allocation or task sequencing (2)
  • (-) Financial (1)

Subscribe to our mailing list

6 ADB Avenue,
Mandaluyong City
1550, Metro Manila,
Philippines

 

Phone: +632 632 4444
Fax: +632 636 2444

Other ADB Websites

ADB Compliance Review Panel
Asia Pathways (ADBI Blog)
Asia Regional Integration Center
Asian Bonds Online
Asian Development Blog
Open Access Repository
Statistical Database System

IED Social Media

LinkedIn

Twitter

YouTube

©2024 Independent Evaluation - Asian Development Bank

Footer

  • About