Jiangxi Ji'an Sustainable Urban Transport Project

In turbulent times, projects must formulate comprehensive contingency plans for major emergencies such as (i) strengthening risk management with flexible plans to address unpredictability, (ii) developing adaptable resource plans, (iii) enhancing supply chain transparency to mitigate delays, (iv) improving remote team collaboration, and (v) leveraging digital technology to monitor projects during emergencies. This project was affected by the pandemic and required a loan extension until 30 June 2022, necessitating a corresponding extension of the implementation period. Despite this, it was highly successful in delivering its intended results.