The designation of the Workforce Development Center as focal agency for the SFK was appropriate. However, its participation in the TA was delayed because of lengthy procedures. For future similar TA projects, ADB should carefully assess government counterpartss readiness, ownership, and capacity to deliver planned outputs and also request toassign properly authorized representatives in the TA implementation units.
Project Name
COVID-19 Solidarity Fund for Kazakhstan
Project Number
54265-001
Report Date
Report Source
Technical assistance completion reports
Country
Sector
Applicability
Project Cycle Stage
Preparation
Implementation
Keywords
OP1: Addressing remaining poverty and reducing inequalities
OP2: Accelerating progress in gender equality
OP6: Strengthening governance and institutional capacity