Earthquake Emergency Assistance Project

Clarify roles and respect existing mandates. Initial delays in implementation of the project were caused by confusion about the roles of new and existing institutions. Any large- scale reconstruction operation requires clear delineation of the mandates of levels of government, to provide the structure and clarity required for all stakeholders to work with maximum efficiency. To the extent possible, the provincial and regional governments and federal agencies should be provided with capacity to perform their mandated roles. This approach may cause initial delays in response to major disasters but builds ownership and sustained capacity to manage completed infrastructure and responses to future disasters.