For components B, E, and H, substantial time was required to mobilize community- based organizations and implementing-partner nongovernment organizations (NGOs) to reach hundreds of villages to be served under major disaster reconstruction programs. This resulted in delays at the start of implementing activities under these components, and support from NGOs was required.
Project Name
Tsunami-Affected Areas Rebuilding Project
Project Number
39144-013
Report Date
Report Source
Self-evaluation
Country
Sector