The project was somewhat overambitious in setting the timelines for achieving the reforms. The government was fully committed to the reforms, but progress depended on the progress of other projects. In this project, two loan covenants were partly complied with at the project completion due their complexity. If reforms are significant, it is useful to consider a phased approach, so that interim achievements can be captured within the project timeframe.
Project Name
Woman and Child Health Development Project
Project Number
36509-013
Report Date
Report Source
Self-evaluation
Country