Construction of sewerage and wastewater treatment plants (WWTP) was substantially delayed due to delays in land acquisition, preparation of a detailed design, and a change of site location. In order to avoid any unnecessary delay in the implementation of the project, sufficient attention should be paid to land acquisition in project preparation, and the land should be made available for the project prior to mobilization of the design consultant.
Project Name
Urban and Environmental Improvement Project
Project Number
32239-013
Report Date
Report Source
Self-evaluation
Country
Sector