A unit to provide technical support to WUSCs should be established in an early stage of the project, and the staff of WUSCs should be trained throughout the project implementation period, rather than just at the end. ADB should be more involved in ensuring that appropriate mechanisms for providing technical support are in place and that the unit's capacity is strengthened. Five regional technical support centers were established very late in the project, and only one center was staffed by two people, who do not know how to operate some of the equipment.