Road Maintenance and Upgrading (Sector) Project

The initial delays due to the lack of consistent and timely project review and oversight from ADB during the first 3 years of the project could not be corrected for a long period, during which time civil works progress fell behind completion targets and disbursement was constantly below expectations. In order to mitigate this, frequent review and close supervision and closely monitoring for in-country procurement processes will be required.