More in-depth involvement by the borrower, executing agency, and implementing agencies in the preparation of the project design is important. The cancellation during the implementation of two subcomponents, which were essential to project sustainability, seemed too late since resources have already been committed. Agreeing to the changes should have triggered the revision of the design and monitoring framework.
Project Name
Road Rehabilitation-2 Project
Project Number
34159-013
Report Date
Report Source
Validation of self-evaluation
Country