The overall time allowed for implementation of the investment and reform programs was inadequate for developing knowledge and understanding, processes, procedures, and the project implementation framework. Unrealistic work schedules, poor procurement planning, insufficient implementation details, and loose monitoring targets prolonged implementation. A well-qualified and experienced project team leader and consultants’ familiarity with ADB processes are essential to implement an ADB-financed project.