Advanced Procurement Action. Early procurement for contract packages is absolutely essential to enable projects to meet their implementation schedule. In this case, the major civil works contract packages for year 1 were prepared by the Local Government Engineering Department (LGED) during the feasibility study before the project consultants were mobilized and the subproject appraisal reports (SARs) were prepared. Early recruitment of the consultants would have improved the performance of the project in the early stages. The recruitment process should be simplified to avoid delays.
Project Name
Rural Infrastructure Improvement Project
Project Number
31304-013
Report Date
Report Source
Self-evaluation