Project implementation capacity of the executing and implementing agencies. The provision of training for the executing and implementing agencies at the outset, not only in ADB procurement procedures but also in project management techniques, would probably have reduced the project start-up delays. Future projects should include appropriate training to new executing and implementing agencies at start-up.