A lack of data and documentation was noted throughout project implementation. The project procurement-related audit noted this, and, as determined by the project completion review mission, data is unavailable within the executing agency. For example, there are no traffic counts after 2009, only two benefit monitoring evaluation reports were available, and the project completion report lacks important information. ADB needs to ensure during project implementation that data requested is provided by the executing agency.