Lao People’s Democratic Republic: Northern Greater Mekong Subregion Transport Network Improvement Project

The accident rate on the project roads was an indicator for the achievement of the project outcome. However, data were unavailable and improvements in road safety could not be assessed quantitatively. The appraisal design should have arranged a way of obtaining accident data.