A need to define more realistic indicators that consider government commitment and capacity to undertake reforms and a timetable to achieve intended results and causal linkages between intended outcome and impact, with expected results having appropriate linkages with policy actions. Most of MPRMP’s policy actions were complied with but many of the outcome and output indicators and targets were not realized. The indicators/targets for development impact were achieved although the outcome and outputs were not met.
Project Name
Mizoram Public Resource Management Program
Project Number
41607-013
Report Date
Report Source
Validation of self-evaluation
Country
Themes
Applicability