When preparing a project for Board approval, ADB should have a thorough knowledge of government procedures for approvals needed to begin project implementation. In the case of this project, ADB should have delayed Board approval until government approval was obtained.
Project Name
Greater Mekong Subregion Kunming–Hai Phong Transport Corridor: Yen Vien–Lao Cai Railway Upgrading Project
Project Number
39175-013
Report Date