Many PNG projects have poor compliance with DMF monitoring due to (i) lack of undertaking baseline studies, (ii) limited measurements of DMF target progress during implementation, and (iii) a lack of BDA who draft and complete a project PCR prior to loan closing. ADB review missions need to monitor these compliance issues more closely and require submission of an updated DMF table prior to each review mission.