Implementing a project in a new field, especially in a dynamically changing transition economy, requires flexibility on the part of both the government and ADB. Willingness to adjust the project's design to a new environment or new findings and acceptance of extra time required for the adjustments is essential. To be successful, the project must also be transparent to receive support from local governments and communities.
Project Name
Community-Based Early Childhood Development Project
Project Number
32143-013
Report Date
Report Source
Self-evaluation
Country