The project framework and design were not updated to reflect changes in scope. The project lacked a clear monitoring framework with defined targets. The project could have benefitted from the revision of the DMF during MTR as these would have provided appropriate measurement of achievements.
Project Name
Railway Sector Improvement Project
Project Number
36317-013
Report Date
Report Source
Self-evaluation
Country