Skip to main content
Evaluation Lessons
  • Home
  • Countries
    • Afghanistan
    • Armenia
    • Azerbaijan
    • Bangladesh
    • Bhutan
    • Brunei Darussalam
    • Cambodia
    • China, People's Republic of
    • Cook Islands
    • Federated States of Micronesia
    • Fiji
    • Georgia
    • Hong Kong, China
    • India
    • Indonesia
    • Kazakhstan
    • Kiribati
    • Kyrgyz Republic
    • Lao People’s Democratic Republic
    • Malaysia
    • Maldives
    • Marshall Islands
    • Mongolia
    • Myanmar
    • Nauru
    • Nepal
    • Niue
    • Pakistan
    • Palau
    • Papua New Guinea
    • Philippines
    • Republic of Korea
    • Samoa
    • Singapore
    • Solomon Islands
    • Sri Lanka
    • Taipei,China
    • Tajikistan
    • Thailand
    • Timor-Leste
    • Tonga
    • Turkmenistan
    • Tuvalu
    • Uzbekistan
    • Vanuatu
    • Viet Nam
    • Australia
    • Japan
    • New Zealand
  • Sectors
    • Agriculture, natural resources, and rural development
    • Education
    • Energy
    • Finance
    • Health
    • Industry and trade
    • Information and communication technology
    • Multisector
    • Public sector management
    • Transport
    • Water and other urban infrastructure and services
  • Themes
    • Inclusive Economic Growth
    • Environmentally Sustainable Growth
    • Regional Integration
    • Private Sector Development
    • Governance and Capacity Development
    • Gender Equity and Mainstreaming
    • Knowledge Solutions
    • Partnerships
  • About
  • Home
  • Countries
  • Sectors
  • Themes
  • About

Western Basins Water Resources Management Project

Proactive approaches to improve procurement readiness, combined with timely effectiveness, will reduce the risk of implementation delays.

Project Name

Western Basins Water Resources Management Project

Project Number
36252-013
Report Date
29 Dec 2020
Report Link
https://www.adb.org/projects/documents/afg-36252-013-pcr
Report Source
Self-evaluation
Country
Afghanistan
Sector
Agriculture, natural resources, and rural development
Agricultural production
Irrigation
Rural water policy, institutional and capacity development
Water-based natural resources management
Themes
Inclusive Economic Growth
Gender Equity and Mainstreaming
Governance and Capacity Development
Partnerships
Report Rating
Successful

Related Lessons

Strong commitment of executing and implementing agencies is instrumental to project success. The project target impact was fully aligned with the…


The text could instead have reflected on the approach to working with regional countries to scale up JCCs, particularly on how contextual…


Benchmarks and indicators are needed to improve urban services delivery and utility performance.


Strong collaboration between the executing agency and the land office from the project planning stage is critical to minimize delays in land…


Baseline information is also critical to ensure adequate project design and monitoring of achievements.


Subscribe to our mailing list

6 ADB Avenue,
Mandaluyong City
1550, Metro Manila,
Philippines

 

Phone: +632 632 4444
Fax: +632 636 2444

Other ADB Websites

ADB Compliance Review Panel
Asia Pathways (ADBI Blog)
Asia Regional Integration Center
Asian Bonds Online
Asian Development Blog
Open Access Repository
Statistical Database System

IED Social Media

LinkedIn

Twitter

YouTube

©2024 Independent Evaluation - Asian Development Bank

Footer

  • About