The TA proposed additional consultant hours to support processing operations. With remaining budget available, this may have been an opportunity for increased utilization of TA-financed personnel to assist or train government staff. The TA generated high quality documents. With the remaining funds, there could have been an opportunity to support the implementation of recommended actions.
Project Name
Southern Highways Investment Program
Project Number
46374-001
Report Date
Report Source
Technical assistance completion reports validation
Country