If a bus rapid transit (BRT) system is planned to traverse a highly populated area with limited road space, the alignment should be properly selected at appraisal with priority consideration given to avoiding traffic congestion.
Project Name
Jiangxi Fuzhou Urban Integrated Infrastructure Improvement Project
Project Number
44007-013
Report Date
Report Source
Self-evaluation
Country
Sector
Applicability
Project Cycle Stage
Preparation