Skip to main content
Evaluation Lessons
  • Home
  • Countries
    • Afghanistan
    • Armenia
    • Azerbaijan
    • Bangladesh
    • Bhutan
    • Brunei Darussalam
    • Cambodia
    • China, People's Republic of
    • Cook Islands
    • Federated States of Micronesia
    • Fiji
    • Georgia
    • Hong Kong, China
    • India
    • Indonesia
    • Kazakhstan
    • Kiribati
    • Kyrgyz Republic
    • Lao People’s Democratic Republic
    • Malaysia
    • Maldives
    • Marshall Islands
    • Mongolia
    • Myanmar
    • Nauru
    • Nepal
    • Niue
    • Pakistan
    • Palau
    • Papua New Guinea
    • Philippines
    • Republic of Korea
    • Samoa
    • Singapore
    • Solomon Islands
    • Sri Lanka
    • Taipei,China
    • Tajikistan
    • Thailand
    • Timor-Leste
    • Tonga
    • Turkmenistan
    • Tuvalu
    • Uzbekistan
    • Vanuatu
    • Viet Nam
    • Australia
    • Japan
    • New Zealand
  • Sectors
    • Agriculture, natural resources, and rural development
    • Education
    • Energy
    • Finance
    • Health
    • Industry and trade
    • Information and communication technology
    • Multisector
    • Public sector management
    • Transport
    • Water and other urban infrastructure and services
  • Themes
    • Inclusive Economic Growth
    • Environmentally Sustainable Growth
    • Regional Integration
    • Private Sector Development
    • Governance and Capacity Development
    • Gender Equity and Mainstreaming
    • Knowledge Solutions
    • Partnerships
  • About
  • Home
  • Countries
  • Sectors
  • Themes
  • About

Uttarakhand Power Sector Investment Program - Tranche 4 and MFF

Thorough institutional capacity assessment is a necessary precondition to determining the most appropriate implementation arrangement.

Project Name

Uttarakhand Power Sector Investment Program - Tranche 4 and MFF

Project Number
37139-053
Report Date
14 Dec 2021
Report Source
Self-evaluation
Country
India
Sector
Energy
Electricity transmission and distribution
Applicability
Project-level
Project Cycle Stage
Preparation
Topics
EA/IA capacity assessment, Implementation arrangement

Related Lessons

Intermittent water supply is more costly both for the ULBs and the beneficiaries in the long run. Intermittent water flow increases the risk of…


Additional resident mission resources could aid in due diligence. Whether this dispute and its potential to disrupt the business could have been…


The project design and monitoring framework included components that are not directly related to the project. The implementation arrangements for…


Inaccurate projections about solar irradiation can lead to suboptimal performance of solar systems.


Municipal governments need to strategize how to achieve wider water supply coverage, including exploring cross-subsidies between industrial/…


Subscribe to our mailing list

6 ADB Avenue,
Mandaluyong City
1550, Metro Manila,
Philippines

 

Phone: +632 632 4444
Fax: +632 636 2444

Other ADB Websites

ADB Compliance Review Panel
Asia Pathways (ADBI Blog)
Asia Regional Integration Center
Asian Bonds Online
Asian Development Blog
Open Access Repository
Statistical Database System

IED Social Media

LinkedIn

Twitter

YouTube

©2024 Independent Evaluation - Asian Development Bank

Footer

  • About