Yunnan Chuxiong Urban Environment Improvement Project

Reducing or avoiding implementation delays would require, among others: (i) ensuring that project and/or subproject implementation is a high priority for local governments and counterpart funds are provided in government annual budgets, and (ii) starting resettlement activities as early as possible and providing adequate funds for these activities.

resettlement activities as early as possible and considering financing the resettlement activities with ADB loan proceeds. Project Gender designs were highly relevant and contributed to achieving the overall project objectives. As this was the first project funded by ADB in Chuxiong prefecture, provision of training on Gender equality and GAP for better understanding of the requirements for GAP implementation were critical for raising awareness and building capacity of the PMO and the IAs staff.