Implementation issues. The long front-end implementation delays from the project serve as a major lesson. The expectations in implementing the project under an emergency modality over 18 months as a sector project over remotely located subproject sites, given the low absorptive capacity of Ministry of Infrastructure Development (MID), may have been unrealistic. For remote subprojects, higher mobilization and demobilization costs should be factored into cost estimates.
Project Name
Emergency Assistance Project
Project Number
41105-012
Report Date
Report Source
Self-evaluation
Country
Sector