Reliable data are essential to identifying problems and monitoring progress. However, the project progress reports often lacked substance, contained stale information, and did not effectively address implementation issues. The requirement of thorough reporting could have been better formulated in the supervision consultant's terms of reference. MOTC needs to review the project progress reports.
Project Name
Southern Transport Corridor Road Rehabilitation Project
Project Number
36257-013
Report Date
Report Source
Self-evaluation
Country