The completion of the project was delayed by about 1 year, primarily due to the failure to finalize cofinancing arrangements with Organization of the Petroleum Exporting Countries (OPEC). This issue might have been avoided if the final solution (financing by the government) had been adopted faster. In the future, the government and ADB need to select cofinancing partners carefully.
Project Name
Southern Transport Corridor Road Rehabilitation Project
Project Number
36257-013
Report Date
Report Source
Self-evaluation
Country