Utility shifting can form part of the item-rate and/or engineering, procurement, and construction(EPC) contracts to facilitate the efficient delivery of future projects. In road construction projects, the shifting of utility is often contracted out by the executing agency to third-party entities specializing in utility shifting. However, this arrangement can be misused as an excuse by some contractors, leading to possible delays in the delivery of contracts. Incorporating utility shifting in the item-rate and/or engineering, procurement, and construction (EPC) contracts may be considered in future projects.