Strong government ownership is critical to achieving results. The Cabinet of Ministers, the and other project agencies had to coordinate closely among themselves to ensure that changes in law, decrees, regulatory changes, and board resolutions were implemented in a timely manner. If any intermediate step had been delayed, this would have resulted in a knock-on effect on other outcomes and resulted in delays in the project timetable. The Ministry of Finance negotiated concurrently for budget support from several development partners.