Solar Transmission Sector Project

Close coordination is required to ensure high utilization of project-financed assets. The executing agency is responsible only for the construction, installation, and commissioning of transmission assets, as required by the National Dispatch Center, while the utilization of assets is the responsibility of the National Dispatch Center. Although the utilization of assets built under this project is satisfactory at present, the executing agency is not aware of the future planned level of utilization. While the executing agency will not be financially affected because the tariff methodology assures that costs will be recovered through a return on equity, any underutilization of assets would have an economic cost.

Project Name

Solar Transmission Sector Project

Project Number
49214-002
Report Date
Report Source
Self-evaluation
Country
Report Rating
Applicability
Project Cycle Stage
Implementation